Task scheduled for nonworking time created as milestoneArticle ID: 113154 - View products that this article applies to. This article was previously published under Q113154 Symptoms
In Microsoft Project, if you create a task by dragging on the Calendar or the Gantt Chart, and you start dragging on a nonworking day and stop dragging on a nonworking day, the task is created as a milestone.
WorkaroundTo avoid creating a milestone task when you create a task in the Gantt Chart by dragging on a view, turn on Advice from Planning Wizard. When the PlanningWizard is turned on, and you drag on the Gantt Chart starting on a nonworking day, you receive the following message You moved '(ID n)' to start on a nonworking day. (startdate)
More informationPlanningWizards do not appear when you edit your project in the Calendar view. Because of this, when you format and edit your project in this view, you receive the same results as when you format and edit your project in the Gantt Chart view with the PlanningWizards turned off.
PropertiesArticle ID: 113154 - Last Review: April 29, 2013 - Revision: 7.0 Applies to
| Article Translations
|


Back to the top