PRJ: Setting Task to 0% or 100% Complete Updates Resource Status

Article translations Article translations
Article ID: 172893 - View products that this article applies to.
This article was previously published under Q172893
Expand all | Collapse all

SYMPTOMS

When you set a task to 0% or 100% complete, the actual work will be set to 0 hours (0h) or the total amount of work, even though you cleared the "Updating task status updates resource status" check box on the Calculation tab in the Options dialog box. (On the Tools menu, click Options.)

CAUSE

This problem occurs because Microsoft Project recalculates a task set to 0% or 100% complete and updates the status of the task. In contrast, Microsoft Project 95 only recalculates a task set to 100% complete.

Properties

Article ID: 172893 - Last Review: September 18, 2011 - Revision: 4.0
APPLIES TO
  • Microsoft Project 2000 Standard Edition
  • Microsoft Project 98 Standard Edition
  • Microsoft Office Project Professional 2007
  • Microsoft Office Project Professional 2003
  • Microsoft Office Project Standard 2007
  • Microsoft Office Project Standard 2003
  • Microsoft Project 2002 Standard Edition
  • Microsoft Project 2002 Professional Edition
  • Microsoft Project Professional 2010
  • Microsoft Project Standard 2010
Keywords: 
kbbug kbfix kbusage KB172893

Give Feedback

 

Contact us for more help

Contact us for more help
Connect with Answer Desk for expert help.
Get more support from smallbusiness.support.microsoft.com