Select the product you need help with
Tasks are not scheduled as expected in Microsoft ProjectArticle ID: 175457 - View products that this article applies to. This article was previously published under Q175457 Summary
This article describes why a task may not be scheduled as expected in Microsoft Project and
offers suggestions for correcting the behavior. More informationA task may not be scheduled as expected for a number of reasons. To determine the exact cause in Project 2010, ask yourself the following questions. Note: Before testing any of the scenarios in this article, make a backup copy of the file or save any changes you might have made to the file. 1. Is the Calculate project after each edit option set to off? When you specify a manual calcualtion, Microsoft Project will calculate your file only when you press F9. Set Calculation to On to resolve scheduling conflicts. To set the calculation method, follow these steps: 2. Is the Show Scheduling Messages option turned off?a. On the File tab, click Options b. Click the Schedule tab. c. Under Calculation, click on either On or Off. If the Show Scheduling Messages option is turned off, changes to the project file that result in scheduling conflicts will be processed. If the Show Scheduling Messages option is turned on, you can see the conflick and correct it. To turn the Show Scheduling Messages option on or off, follow these steps: 3. Are you scheduling from the project's Start Date or the project's Finish Date?a. On the File tab, click Options. NOTE: After scheduling messages are turned on, press F9 on the keyboard. Any scheduling messages that occur must be resolved before the project will be calculated correctly.b. Click the Schedule tab. c. Click to select or clear the Show Scheduling Messages check box. d. Click the Advanced tab. e. Under Planning Wizard, select all check boxes. When scheduling from the project's Start Date, the task will begin as soon as possible. When scheduling from the project's Finish Date, the tasks will begin as late as possible. To check which date is set in your file, click Project Information on the Project tab. 4. What is the project's Start Date?If the Show Scheduling Messages option is turned on, and you enter a task that occurs before the project's Start Date, you will receive a warning message. If you want to schedule a task to start before the porject's Start Date, manually enter the date for the task. To check the Project Start Date, click Project information on the Project tab. 5. Did you enter a percent complete on a task?If you entered a percent complete on a task, and the task has already started, you cannot change the Start Date automatically. To determine where the task would schedule automatically, set the task to zero percent complete. To do this, follow these steps: 6. Did you assign an Actual Start Date to the task?a. Select the task. b. On the Task tab, click Task Information. c. Click the General tab. d. In the Percent Complete box, type 0. e. Click OK. You can assign an Actual Start Date to a task and not enter a percent complete. The task will not be scheduled automatically unless you set the Actual Start Date to NA. To set the Actual Start Date, insert the actual start field into your table. To do this, follow these steps: 7. Did you assign a constraint type other than As Soon As Possible (ASAP) to the task?a. Select the title of any column currently in your table. b. On the Format tab, click Insert Column. c. Select Actual Start for the Field Name and click OK. A contraint can cause a task to be scheduled according to the type of constraint and the date set. In Microsoft Project, a task that has the constraint of As Late As Possible (ALAP) task in a project that is scheduled from the project's Finish Date. To check the constraint type, follow these steps: 8. Are there any predecessor or successor relationships?a. Double-click the ID number for the task. b. Click the Advanced tab. The type of relationship will determine when the task can be scheduled. In Microsoft Project, the Task will always honor their constraint dates setting overrides the task relationship links. To set this option, follow these steps: 9. Are you using automatic Resource Leveling?a. On the File tab, click Options. b. Click the Schedule tab. c. Click to select the Tasks will always honor their contraints dates check box. d. Click OK. Automatic resource leveling will add delay to a task to avoid resource conflicts. This results in the task Start Date being pushed out. If you select the Manual option, delay will not be added to tasks automatically. To remove any delay added to a task and to set resource leveling to manual, do the following: 10. Is there a value in the Task Delay field?* To remove delay, click Clear Leveling on the Resource tab. * To set resource leveling to manual, click Leveling Options on the Resource tab, and then click Manual. If the Task Delay field contains a value greater than zero, you cannot schedule the task earlier. To clear the Delay field, see step 9. 11. Is the task a subtask?If a Summary task (at any level) has a predecessor or a constrain, the subtask cannot be scheduled any earlier than the summary task. To check a summary task for predecessors or constraints, follow these steps: 12. Is there a resource assigned to the task?a. Select the task. b. On the Task tab, click Task Information. The resource calendar can affect the scheduling of a resource-driven task but not a fixed duration task. In Microsoft Project, the resource calendar can affect all three task types (fixed duration, fixed work, and fixed units). Remove the resource to see if, in fact , the resource is affecting the scheduling. After the resource is removed, if the task schedules as expected, then check the resource's calendar. To check the Resoure calendar, follow these steps: 13. Are you trying to schedule a task during a non-working time?On the Project tab, click Change Working Time, and then select the resource name from the drop down list. If a day is marked as non-working, then you cannot schedule a task to start on that day. To check the Project Calendar, click Change Working Time on the Project tab. 14. Are there any predecessor or successor relationships assigned to summary tasks?Predecessor and Successor relationships assigned to summary task can affect sub task of the summary task in addition to the summary task(s) that are linked. The type of relationship will determine when the task can be scheduled. In Microsoft Project, the Tasks will always honor their constraint dates setting overrides the task relationship links. Earlier versions of Microsoft Project do not have this option. To set this option, follow these steps: a. On the File tab, click Options. b. Click the Schedule tab. c. Click to select the Task will always honor their contraint dates check box. d. Click OK. To determine the exact cause in Project 2007 and earlier versions, ask yourself the following questions. Note Before testing any of the scenarios in this article, make a backup copy of the file or save any changes you might have made to the file.
PropertiesArticle ID: 175457 - Last Review: March 26, 2013 - Revision: 8.1 Applies to
| Article Translations
|


Back to the top








