Symptoms

In Microsoft Project, if two tasks are linked in a predecessor/successor relationship and you indent the successor to make it a subtask and the predecessor of a summary task, you may receive the following error message:

This outline change would create a circular relationship.

Indenting these tasks would create an illogical relationship with other tasks.

Check the task dependencies for the tasks from which you are indenting, and then try again.

Cause

This problem occurs when the predecessor task has a cross-project link as a predecessor and the task you are trying to subordinate is its successor. For example, let's say you have two tasks (A and B). They are linked by a Finish to Start relationship and Task A has a cross-project link to a task in another project. If you indent task B under Task A, you will receive this error message.

Workaround

To work around this problem, remove the predecessor and successor link between the tasks and then indent the task.

Properties

Article ID: 176293 - Last Review: March 7, 2013 - Revision: 7.0
Applies to
  • Microsoft Office Project Professional 2007
  • Microsoft Office Project Professional 2003
  • Microsoft Office Project Standard 2007
  • Microsoft Office Project Standard 2003
  • Microsoft Project Professional 2010
  • Microsoft Project Standard 2010
  • Microsoft Project 2013 Professional
  • Microsoft Project 2013 Standard
Keywords: 
kbbug kbpending kbusage KB176293

Give Feedback

 

Contact us for more help

Contact us for more help
Connect with Answer Desk for expert help.
Get more support from smallbusiness.support.microsoft.com