PRJ: Start Or Finish Date Changed When Typing A New Date In Network Diagram or Task Form View

Article translations Article translations
Article ID: 245843 - View products that this article applies to.
This article was previously published under Q245843
Expand all | Collapse all

SYMPTOMS

In Microsoft Project, when you type a start or finish date for a task in Network Diagram view or Task Form view, the task may be scheduled to the next working day without notification.

CAUSE

When you enter a start or finish date in Network Diagram view or Task Form view that is a nonworking day for a task, the date is automatically changed to the next working day.

If you enter a date that is a nonworking day in another view, such as the Gantt Chart view, the Planning Wizard will notify you that the day you entered is a nonworking day. This message does not appear in the Network Diagram or Task Form views because these views have fewer events that will be displayed by the Planning Wizard than other views.

WORKAROUND

To work around this behavior, type start or finish dates in a view other than the Network Diagram or the Task Form views. For example, type start or finish dates in Gantt Chart view.

STATUS

Microsoft has confirmed that this is a problem in the Microsoft products that are listed at the beginning of this article.

Properties

Article ID: 245843 - Last Review: September 18, 2011 - Revision: 3.0
APPLIES TO
  • Microsoft Project 2000 Standard Edition
  • Microsoft Office Project Professional 2007
  • Microsoft Office Project Professional 2003
  • Microsoft Office Project Standard 2007
  • Microsoft Office Project Standard 2003
  • Microsoft Project 2002 Standard Edition
  • Microsoft Project 2002 Professional Edition
  • Microsoft Project Professional 2010
  • Microsoft Project Standard 2010
Keywords: 
kbbug kbpending KB245843