Article ID: 260425 - Last Review: January 27, 2007 - Revision: 1.2 PRJ2000: Cannot View Status Reports After You Merge Manager AccountsThis article was previously published under Q260425 On This PageSYMPTOMS
In Microsoft Project Central, the following symptoms may occur:
CAUSE
This behavior occurs when a status request was sent from a manager's account (account A), and that account was then merged into another manager's account (B). The resulting new manager account (B) cannot see the status updates that are made by the resources. The code for merging accounts does not update records in certain tables pertaining to the current manager for a project. RESOLUTION
To resolve this problem, obtain Microsoft Project 2000, Service Release 1 (SR-1). To obtain SR-1, click the article number below to view the article in the Microsoft Knowledge Base: 288953
(http://support.microsoft.com/kb/288953/EN-US/
)
PRJ2000: How to Obtain and Install Microsoft Project 2000 SR-1
Temporary WorkaroundTo temporarily work around this problem in Microsoft Project 2000 (non-SR-1), have the resources re-send the status reports with the same information.NOTE: The workaround may not always resolve this issue, so installing SR-1 is recommended. STATUSMicrosoft has confirmed that this is a problem in the Microsoft products that are listed at the beginning of this article.
This problem was corrected in Microsoft Project 2000, Service
Release 1 (SR-1).