Article ID: 266012 - Last Review: January 27, 2007 - Revision: 1.1 PRJ2000: Work Total Greater Than Expected After You Remove Resource from Summary TaskThis article was previously published under Q266012 On This PageSYMPTOMS
In Microsoft Project, the total work value for a summary task may be greater than the sum of the work values for all resources assigned to the summary task and its subtasks.
CAUSE
This problem occurs when the following conditions are true:
RESOLUTION
To resolve this problem, obtain Microsoft Project 2000, Service Release 1 (SR-1). To obtain SR-1, click the article number below to view the article in the Microsoft Knowledge Base: 288953
(http://support.microsoft.com/kb/288953/EN-US/
)
PRJ2000: How to Obtain and Install Microsoft Project 2000 SR-1
Temporary WorkaroundTo temporarily work around this problem, use either of the following methods.Method 1Use the Assign Resources dialog box to assign and then remove a resource on the summary task that has the incorrect work value. To do this, follow these steps:
Method 2Use the Resource Usage view to change the assignment work for the Unassigned resource associated with the summary task to zero. To do this, follow these steps:
STATUSMicrosoft has confirmed that this is a problem in the Microsoft products that are listed at the beginning of this article.
This problem was corrected in Microsoft Project 2000, Service
Release 1 (SR-1).