Select the product you need help with
PSRV2002: Timephase %Complete for Non-Working Days Is Not Calculated When You Update Actual Work from Project Web AccessArticle ID: 306220 - View products that this article applies to. This article was previously published under Q306220 On This PageSYMPTOMSIf you enter actual work on days that are defined as
non-working days in the Task Usage view from Microsoft Project Web Access,
Timephased %Complete on the non-working days may be empty or might not be
calculated correctly in the project. CAUSEThis problem occurs because the value for Timephased
%Complete does not record on days that are defined as non-working
days. RESOLUTIONService Pack InformationThis problem is corrected in Project Server 2002 Service Pack 1.To resolve this problem, obtain the latest service pack for Project Server 2002. For additional information, click the following article number to view the article in the Microsoft Knowledge Base: 867830
(http://support.microsoft.com/kb/867830/
)
How to obtain the latest Microsoft Project Server 2002 service packHotfix InformationA supported fix is now available from Microsoft, but it is only intended to correct the problem that is described in this article. Apply it only to computers that are experiencing this specific problem.To resolve this problem, contact Microsoft Product Support Services to obtain the fix. For a complete list of Microsoft Product Support Services phone numbers and information about support costs, visit the following Microsoft Web site: http://support.microsoft.com/default.aspx?scid=fh;EN-US;CNTACTMS NOTE: In special cases, charges that are ordinarily incurred for
support calls may be canceled if a Microsoft Support Professional determines
that a specific update will resolve your problem. The usual support costs will
apply to additional support questions and issues that do not qualify for the
specific update in question.
(http://support.microsoft.com/default.aspx?scid=fh;EN-US;CNTACTMS)
The English version of this fix should have the following file attributes or later. The dates and times for these files are listed in Coordinated Universal Time (UTC). When you view the file information, it is converted to local time. To find the difference between UTC and local time, use the Time Zone tab in the Date and Time tool in Control Panel. Client Side Date Time Size File name ------------------------------------------------- 09-Oct-2002 23:30 8,859,648 Project10.msp Server Side Date Time Size File name ------------------------------------------------- 09-Oct-2002 23:52 3,524,608 Prjsvr10.msp Client Side Date Time Version Size File name -------------------------------------------------------------- 22-May-2002 22:37 10.0.4109.0 7,445,320 Owc10.dll 09-Oct-2002 19:31 10.0.2002.1009 909,824 Pj10od10.dll 09-Oct-2002 19:31 10.0.2002.1009 4,108,800 Pjoledb.dll 09-Oct-2002 19:31 10.0.2002.1009 10,101,248 Winproj.exe Server Side Date Time Version Size File name -------------------------------------------------------------- 30-Aug-2002 00:13 611 Build.inc 05-Sep-2002 19:19 6,133 Clntutil.asp 05-Sep-2002 19:19 13,525 Dlmain.asp 05-Sep-2002 19:19 6,946 Issshell.asp 05-Sep-2002 19:19 16,837 Linkissu.asp 05-Sep-2002 19:19 3,975 New4task.asp 17-Sep-2002 00:56 10.2002.0.916 626,688 Pds.dll 09-Oct-2002 19:31 10.0.2002.1009 909,824 Pj10od10.dll 29-Aug-2002 19:20 914,153 Pjclient.cab 01-Oct-2002 01:00 10.0.2002.930 167,936 Pjobjprv.dll 09-Oct-2002 19:31 10.0.2002.1009 4,108,800 Pjoledb.dll 06-Aug-2002 18:16 3,584 Prjsvre.mst 05-Sep-2002 19:19 53,683 Svrdbdl.asp WORKAROUNDTo work around this issue, modify the Enterprise Global
Calendar to contain all working days. STATUSMicrosoft
has confirmed that this is a problem in the Microsoft products that are listed
at the beginning of this article.
This problem was first corrected in Project Server 2002 Service Pack 1. REFERENCES For additional information
about how %complete is calculated, click the following article number to view
the article in the Microsoft Knowledge Base: 101495
(http://support.microsoft.com/kb/101495/EN-US/
)
PRJ: How Percent Complete Is
Calculated for Nested Summary Tasks
PropertiesArticle ID: 306220 - Last Review: September 18, 2011 - Revision: 3.0
|


Back to the top








