Select the product you need help with
Changes to subtasks are not reflected in the summary taskArticle ID: 312379 - View products that this article applies to. This article was previously published under Q312379 On This PageSymptoms
In Microsoft Project, when you make changes to a subtask, those changes may not be reflected in the summary task for that subtask. For example, if you change the amount of work on a subtask, the total Work value at the summary level may not adjust appropriately. Cause
This problem may occur if the Calculation options for Microsoft Project setting is Manual.
In Project 2010 and later this may occur if the summary task is set to Manually Scheduled Task Mode and/or Calculate this project after each edit is Off. ResolutionProject 2010, 2013Method 1:Change the Task Mode for the summary task to Automatically Scheduled. To do this, follow these steps:
Note: Although the default task mode for new tasks in Project 2010 and 2013 is Manually Scheduled, you can change if for all new tasks. On the Task tab, in the Schedule group, click Mode, and then click Auto Schedule. All tasks entered in this project will have a default task mode of Automatically Scheduled. Methode 2: Change the Calculate this project after each edit setting to ON To do this, follow these steps:
Project 2003, 2007To work around this problem, change the Calculation options for Microsoft Project setting to Automatic. To do this, follow these steps:
Status
This behavior is by design. PropertiesArticle ID: 312379 - Last Review: March 25, 2013 - Revision: 9.0 Applies to
|


Back to the top








