Definition of Microsoft Project constraintsArticle ID: 74978 - View products that this article applies to. This article was previously published under Q74978 Summary
Each constraint type in Microsoft Project can be defined as a formula using
the following conventions:
ES = Early Start of the activity LS = Late Start of the activity EF = Early Finish of the activity LF = Late Finish of the activity SS = Scheduled Start of the activity SF = Scheduled Finish of the activity CD = Constraint Date More information
The following are definitions of Microsoft Project constraints.