Each constraint type in Microsoft Project can be defined as a formula using
the following conventions:
ES = Early Start of the activity
LS = Late Start of the activity
EF = Early Finish of the activity
LF = Late Finish of the activity
SS = Scheduled Start of the activity
SF = Scheduled Finish of the activity
CD = Constraint Date
The following are definitions of Microsoft Project constraints.
For more information on Contraints, please see the "Microsoft Project for
Windows Reference" or query on:
winproj and constraint