Article ID: 835320 - Last Review: July 27, 2006 - Revision: 3.3 The Actual Work field may display a zero (0) instead of the actual work hours that you submitted in the custom Project Center view in Microsoft Project Web AccessOn This PageSYMPTOMSIf you create a custom Project Center view in Microsoft
Project Web Access, the Actual Work field may display a zero
(0) instead of the actual work hours that you submitted. RESOLUTIONThis problem was first fixed in a hotfix that is now contained in a service pack. If you installed the latest Project Server 2003 service pack, you do not have to install the hotfix. Service pack informationThis problem is corrected in Project Server 2003 Service Pack 1.To resolve this problem, obtain the latest service pack for Project Server 2003. For additional information, click the following article number to view the article in the Microsoft Knowledge Base: 873458
(http://support.microsoft.com/kb/873458/
)
How to obtain the latest service pack for Project Server 2003 Hotfix informationHow to obtain the hotfixThis issue is fixed in the Microsoft Office Project Server 2003 Hotfix Package that is dated January 22, 2004. For additional information, click the following article number to view the article in the Microsoft Knowledge Base:835217
(http://support.microsoft.com/kb/835217/
)
Description of Microsoft Office Project Server 2003 hotfix package: January 22, 2004 Important Applying this hotfix will not correct the problem that is described in the "Symptoms" section for your existing custom view in Microsoft Project Web Access. After you apply this hotfix, see the "More Information" section. STATUSMicrosoft has confirmed that this is a problem in the Microsoft products that are listed in the "Applies to" section. This problem was first corrected in Project Server 2003 Service Pack 1. MORE INFORMATIONAfter you apply the hotfix that is described in the
"Resoluction" section, you must remove and then re-add the
Actual Work field in your custom view in Microsoft Project Web
Access. After you re-add the Actual Work field, save the
changes to your custom view.