Article ID: 840314 - Last Review: April 7, 2006 - Revision: 3.4 Task data may disappear or value custom field values in a task may be missing when you make changes to enterprise custom fields in your Master Project File in Project 2003On This PageSYMPTOMSWhen you make changes to enterprise custom fields in your
Master Project File in Microsoft Office Project 2003, enterprise custom field
values that are contained in a task may be missing from the inserted file, and other task data may randomly disappear. Additionally, when you save a file, you may receive a SQL error message that is similar to the following: [Microsoft][ODBC SQL Server Driver][SQL Server]Cannot insert duplicate key row in object 'MSP_TASK_BASELINES'with unique index 'I_MSP_TASK_BASELINES' CAUSEThis problem may occur if all the following conditions are
true:
RESOLUTIONService pack informationThis problem is corrected in Project 2003 Service Pack 1.To resolve this problem, obtain the latest service pack for Project 2003. For additional information, click the following article number to view the article in the Microsoft Knowledge Base: 873459
(http://support.microsoft.com/kb/873459/
)
How to obtain the latest service pack for Project 2003 Hotfix informationHow to obtain the hotfixThis issue is fixed in the Microsoft Project 2003 Hotfix Package that is dated April 21, 2004. For additional information, click the following article number to view the article in the Microsoft Knowledge Base:840659
(http://support.microsoft.com/kb/840659/
)
Microsoft Office Project 2003 hotfix
package: April 21, 2004 STATUSMicrosoft
has confirmed that this is a problem in the Microsoft products that are listed
in the "Applies to" section. This problem was first corrected in Project 2003 Service Pack 1.