Article ID: 873330 - Last Review: April 7, 2006 - Revision: 2.2 Proposed resources receive e-mail notifications from Project Server 2003On This PageSYMPTOMSResources receive e-mail notifications about the tasks that
are assigned to them, even though the resources are proposed resources. This
issue occurs when the following conditions are true:
RESOLUTIONHow to obtain the hotfixThis issue is fixed in the Project Server 2003 Hotfix Package that was released August 18, 2004. For additional information, click the following article number to view the article in the Microsoft Knowledge Base:838882
(http://support.microsoft.com/kb/838882/
)
Description of the Project Server 2003 post-Service Pack 1 hotfix package: August 18, 2004 Note After you install the hotfix, e-mail notifications are suppressed if the following conditions are true:
However, if the booking type is later changed from Proposed to Committed, and if everything is republished by using the Publish All command, e-mail notifications are sent to the resource. To generate an e-mail notification to the resource, you must select Republish Assignments and then verify that the Notify all affected resources via e-mail check box is selected. STATUSMicrosoft
has confirmed that this is a problem in the Microsoft products that are listed
in the "Applies to" section.