Article ID: 913495 - Last Review: January 19, 2006 - Revision: 1.3 The values for actual work and remaining work in Project Server 2003 do not match the values for actual work and remaining work in Project Professional 2003SYMPTOMSWhen you use Microsoft Project Web Access to view a task in Microsoft Office Project Server 2003, the values for actual work and remaining work in Project Server 2003 do not match the values for actual work and remaining work in Microsoft Office Project Professional 2003. CAUSEThis issue may occur in different scenarios. For example, this issue occurs if you update the task in Project Web Access and then click Cancel when you receive the following message:Note This issue does not occur if you click OK when you receive this message. WORKAROUNDTo work around this issue, you must republish work assignments and overwrite the work that was entered by resources. To do this, follow these steps: