Multiple change orders for the same project line item Content provided by Microsoft TechKnowledge Content Question: I have a budget line item on my project that I may need to do more than one change order for. Can I do that?Answer: Yes, as long as you don’t have more than one change order in a Pending status for either the baseline or the forecast with that project’s cost category on it. The same budget line item can be on as many Unapproved or Approved change orders as you wish. It can also be on two Pending change orders if one is for the baseline and the other is for the forecast. It just can’t be on more than one Pending change order for the forecast or for the baseline.This article was TechKnowledge Document ID: 25075 Last Updated: 10 Mar 2017 Was this information helpful? Yes No Tell us what we can do to improve the article Submit Thanks! Your feedback will help us improve the support experience.