If you want a task to end on a particular day, set a finish date for the task.

  1. Right-click a task, click Information > Advanced tab.

  2. Next to Constraint type, click Must Finish On.

  3. Next to Constraint date, fill in your end date.

Tip:  To set the finish date back to its original setting, change the Constraint type to As Soon As Possible.

Set a deadline for a task

Keep in mind that setting the finish date can lock up your schedule in ways you don’t want. If you just need a reminder, use the Deadlinebox instead. That will create an arrow on the Gantt chart and an indicator in the Indicator column that changes color when the deadline is passed.

  1. Right-click a task, click Information > Advanced tab.

  2. Next to Deadline,fill in your deadline date.

Learn other ways to control the dates in your schedule.

Top of Page

Need more help?

Expand your skills
Explore Training
Get new features first
Join Microsoft Office Insiders

Was this information helpful?

What affected your experience?

Thank you for your feedback!

×