Use the Dates and Intervals tab in the Progress Lines dialog box to set preferences for the way you want to display dates and intervals with progress lines. You can:

  • Display progress lines at regular intervals.

  • Display progress lines based on a specific status date.

  • Display progress lines for specific dates you select.

  • Display progress lines compared with the baseline plan or to the actual plan.

Dialog box location

Display a Gantt Chart view. On the Tools menu, point to Tracking, and then click Progress Lines. Click the Dates and Intervals tab.

Details

Always display current progress line section

Always display current progress line     Select to always display a current progress line.

At project status date     Select to show the current progress line at the project status date. If no project status date has been set, the progress line shows at the current date.

At current date     Select to show the current progress line at the current date.

Display progress lines at recurring intervals section

Display progress lines at recurring intervals     Select to display progress lines at recurring intervals that you select. You can choose daily, weekly, or monthly intervals.

Daily

Daily     Select to show progress lines at a daily interval. You can show progress lines every day, every work day, or at a regular interval, such as every third day. Then in the Daily section, click day or workday, and then click the frequency in the box to specify the frequency of progress lines. You can select a frequency from every day or every work day to every twelfth day or work day.

Weekly

Weekly     Select to show progress lines at a weekly interval (which is the default). For example, you can show progress lines every other Tuesday. Then in the Weekly section, select the frequency in the week on box to specify the frequency of progress lines. You can select a frequency from every week to every twelfth week. Select the check box to specify the day of the week on which you want to display progress lines.

Monthly

Monthly     Select to show progress lines at a monthly interval. For example, you can show progress lines on the last day of every month. Then in the Monthly section that appears, specify your monthly progress line options. If you want to show progress lines on a particular day of the month, clickDay, and then choose the specific day of that month. If you want to show progress lines on a relative day of the month, clickThe, and then select the date options from the boxes. The first date box specifies either the first or last day of the indicated month on which you want to show the lines.

Begin at     Select Project Start to specify that you want to show progress lines from the project start date. Select the option button next to the date box if you want to show progress lines beginning from another date you specify.

Display selected progress lines section

Display selected progress lines     Select this check box and then enter dates in the Progress Line Dates list to specify dates on which to show progress lines.

Progress Line Dates    Enter the dates for which you want to show progress lines.

Delete     Click to remove a selected date from the Progress Line Dates list.

Display progress lines in relation to section

Actual plan     Click to display progress lines in relation to the actual plan.

Baseline plan     Click to display progress lines in relation to the baseline plan.

Need more help?

Want more options?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.

Was this information helpful?

What affected your experience?
By pressing submit, your feedback will be used to improve Microsoft products and services. Your IT admin will be able to collect this data. Privacy Statement.

Thank you for your feedback!

×