PROBLEM

Consider the following scenario.
  • In a SharePoint Online library, you create a Calculated column.
  • You set the data type for the column to Date and Time.
  • You create a Gantt view for the list. When you do this, you specify either the Start Date or the Due Date as the calculated column.
  • When you view the Gantt chart, the date from the calculated column value isn’t displayed on the graph.

MORE INFORMATION

This issue occurs because calculated columns aren’t supported in a Gantt view in SharePoint Online when they're used to display the Start Date or Due Date.