PRJ2000: Assignment Units Changed When You Replace a Resource

Support for Office 2003 has ended

Microsoft ended support for Office 2003 on April 8, 2014. This change has affected your software updates and security options. Learn what this means for you and how to stay protected.

This article has been archived. It is offered "as is" and will no longer be updated.
Symptoms
When you use the Replace Resource dialog box to replace a resource and specify a Units value, Microsoft Project may replace the Units value with a different value than you typed.

When you replace a resource on an in-progress task, the replacement resource is assigned at the same Units as the resource being replaced, regardless of the Units you type in the Replace Resource dialog box.

NOTE: This can cause a work resource to be overallocated if the replacement resource's Maximum Units is less than the value assigned to the resource being replaced.
Cause
This behavior occurs when the following conditions are true:
  1. You have a task that meets the following conditions:

    • At least one resource is assigned.

      -and-

    • %Complete is greater than zero.
  2. You replace the resource assigned to the task and the following conditions are true:
    • You replace the resource by clicking Replace in the Resource Assignment dialog box.

      -and-

    • In the Replace Resource dialog box, you specify a Units value that is different than the original resource's Units.
Workaround
To work around this problem in Project 2010, after you replace the resource, follow these steps:
  1. On the View tab, click Task Usage.
  2. Select the resource assignment for the resource that you assigned to the incomplete protion of the task (the replacement resource).
  3. On the Format tab, click Assignment Information
  4. On the General tab, change the Work and Units boxes to values that reflect the values that you want the resources to work.
  5. For example, suppose the replacement resource is assigned 8h Work with Units of 100 percent. If you want the replacement resource to be assigned at 50 percent insteasd of 100 percent, and you also want to reduce the 8h Work to 50 percent, then change the Units box to 50%, and change the Work box to 4h. If you want the replacement resource to be assigned at 50 percent instead of 100 percent, but you want the resource to complete the remaining 8h Work, then change the Units box to 50%, but do not change the Work box.
  6. Click OK.

To work around this problem in Project 2007 and earlier versons, after you replace the resource, follow these steps:
  1. On the View menu, click Task Usage.
  2. Select the resource assignment for the resource that you assigned to the incomplete portion of the task (the replacement resource).
  3. On the Project menu, click Assignment Information.
  4. On the General tab, change the Work and Units boxes to values that reflect the values that you want the resource to work.

    For example, suppose the replacement resource is assigned 8h Work with Units of 100 percent. If you want the replacement resource to be assigned at 50 percent instead of 100 percent, and you also want to reduce the 8h Work by 50 percent, then change the Units box to 50%, and change the Work box to 4h. If you want the replacement resource to be assigned at 50 percent instead of 100 percent, but you want the resource to complete the remaining 8h Work, then change the Units box to 50%, but do not change the Work box.
  5. Click OK.
Status
Microsoft has confirmed that this is a problem in the Microsoft products that are listed at the beginning of this article.
Properties

Article ID: 245858 - Last Review: 01/06/2015 05:12:58 - Revision: 4.0

  • Microsoft Project 2000 Standard Edition
  • Microsoft Office Project Professional 2007
  • Microsoft Office Project Professional 2003
  • Microsoft Office Project Standard 2007
  • Microsoft Office Project Standard 2003
  • Microsoft Project 2002 Standard Edition
  • Microsoft Project 2002 Professional Edition
  • Microsoft Project Professional 2010
  • Microsoft Project Server 2010
  • Microsoft Project Standard 2010
  • kbnosurvey kbarchive kbbug kbpending KB245858