Date from a calculated column isn’t displayed in a Gantt view in SharePoint Online

PROBLEM
Consider the following scenario.
  • In a SharePoint Online library, you create a Calculated column.
  • You set the data type for the column to Date and Time.
  • You create a Gantt view for the list. When you do this, you specify either the Start Date or the Due Date as the calculated column.
  • When you view the Gantt chart, the date from the calculated column value isn’t displayed on the graph.
MORE INFORMATION
This issue occurs because calculated columns aren’t supported in a Gantt view in SharePoint Online when they're used to display the Start Date or Due Date.

Still need help? Go to the Office 365 Community website.
Properties

Article ID: 3076958 - Last Review: 07/06/2015 21:51:00 - Revision: 2.0

Microsoft SharePoint Online

  • o365 o365e o365p o365a o365m o365022013 kbbug kbnofix KB3076958
Feedback