Question:


I want to make changes to just a Manufacturing (active) routing without changing the planning routing first, how can I do this? What window should I use? 


Answer:


You will want to use the following window to Manufacturing Order Routing Sequence Edit (Transactions - Manufacturing - Manufacturing Order - Go To Button -  MO Routing Sequence Edit) to change the Manufacturing routing without changing the planning routing. 