Committed costs not correctly reflected for purchase orders with change management enabled

Symptoms

Committed costs not correctly reflected for purchase orders with change management enabled

Resolution

The changes in this hotfix will calculate the committed costs correctly for purchase orders with change mnagement enabled.

More information

Note This is a "FAST PUBLISH" article created directly from within the Microsoft support organization. The information contained here in is provided as-is in response to emerging issues. As a result of the speed in making it available, the materials may include typographical errors and may be revised at any time without notice. See Terms of Use for other considerations.