Team member resourcing is problematic with intercompany resources

Symptoms

Users specified as workers and as intercompany resources are not available as Resources in the "Specify Resource Hours" and "Schedule Planning" forms.

Resolution

The changes in this hotfix include:

  • Fix for intercompany worker resource behavior by properly setting the ResourceLegalEntity of an intercompany worker when adding them to a project.

More information

Note This is a "FAST PUBLISH" article created directly from within the Microsoft support organization. The information contained here in is provided as-is in response to emerging issues. As a result of the speed in making it available, the materials may include typographical errors and may be revised at any time without notice. See Terms of Use for other considerations.