Unique ID Successors (task field)

Data Type    Integer List

Entry Type    Entered

Description    The Unique ID Successors field lists the unique ID numbers for the successor tasks to a task. A task must start or finish before successor tasks can start or finish. Each successor is linked to the task by a specific type of task dependency and a lead time or lag time.

Best Uses    Add the Unique ID Successors field to a task view when you want to display or update task successors by their unique ID rather than task ID. Each successor is represented by its unique ID number, which may be followed by a dependency and the lead or lag time. The dependency types for successors are FS (finish-to-start), FF (finish-to-finish), SS (start-to-start), and SF (start-to-finish). To enter lead time, type a negative number. To enter lag time, type a positive number.

Example    You want to review the successors of tasks in your project to analyze and refine the schedule. You add the Unique ID field and the Unique ID Successors field to the Task Sheet view. In the Unique ID Successors field for the "Develop estimate" task, you see the entry "14FS+3d" meaning that the task with Unique ID14 is a successor of this task, with a finish-to-start dependency, and a 3-day lag time. Before the task with Unique ID14 can start, it must wait 3 days after the finish of this task. You also see that the Unique ID Successors field for the "Conduct client meetings" task is blank. You type "15FS" to link this task to the task with unique ID15 with a finish-to-start dependency.

Remarks    If you enter only the task unique ID number in the Unique ID Successors field, Project assumes a finish-to-start dependency with zero lag time. If there is more than one successor, they are all listed and separated by the list-separator character, which is typically the comma.

You can use the Link Tasks command on the Edit menu to link the selected tasks with finish-to-start dependencies and zero lag time. You can also link tasks by dragging from one task to the other on the chart portion of the Gantt Chart or Network Diagram.

If a successor is a task in another project, the Unique ID Successors field also contains the path to the linked project, in addition to the task's Unique ID and dependency type. An example is: C:\My Documents\Bldg E Construction.mpp\3FF.

Bạn cần thêm trợ giúp?

Phát triển kỹ năng Office của bạn
Khám phá nội dung đào tạo
Sở hữu tính năng mới đầu tiên
Tham gia Người dùng nội bộ Office

Thông tin này có hữu ích không?

Cảm ơn phản hồi của bạn!

Cảm ơn bạn đã phản hồi! Để trợ giúp tốt hơn, có lẽ chúng tôi sẽ kết nối bạn với một trong những nhân viên hỗ trợ Office của chúng tôi.

×