Add a task to your timesheet in Project Online

Tasks assigned to you that are scheduled for the dates in the current timesheet period will be automatically included on your timesheet. Sometimes, however, you might start work on a task early, for example, and need to add a task to your timesheet that isn’t automatically included. You can add a task to your timesheet, and your time will be accounted for in the project.

  1. Click the Timesheet tab on the ribbon.

    Timesheet tab

  2. Click Add Row, and then choose the kind of task you want to add.

    Add Row

After adding the task, you can enter your hours for that task.

Kas vajate veel abi?

Kas soovite rohkem valikuvariante?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.

Kas sellest teabest oli abi?

Mis mõjutas teie hinnangut?
Kui klõpsate nuppu Edasta, kasutatakse teie tagasisidet Microsofti toodete ja teenuste täiustamiseks. IT-administraator saab neid andmeid koguda. Privaatsusavaldus.

Täname tagasiside eest!

×