Symptoms


Consider the following scenario:
  • You have a computer that has Microsoft SQL Server 2012 PowerPivot for Microsoft SharePoint 2013 installed.
  • You upload a PowerPivot workbook to a PowerPivot gallery.
  • You schedule data refresh for the PowerPivot workbook.
  • You make some modifications to the PowerPivot workbook, and then you save the changes.
In this scenario, the scheduled data refresh is disabled unexpectedly.

Resolution


The issue was first fixed in the following cumulative update of SQL Server.

Cumulative Update 6 for SQL Server 2012 SP1

Status


Microsoft has confirmed that this is a problem in the Microsoft products that are listed in the "Applies to" section.

More Information


For more information about how to schedule data refresh, go to the following Microsoft TechNet website: