Outline tasks in a project
Indent and outdent tasks to show hierarchy. An indented task becomes a subtask of the task above it, which becomes a summary task.
- 
                      Select View > Task Views > Gantt Chart. 
- 
                      Select the task or tasks in the Task Name column that you want to indent or outdent. 
- 
                      Do one of the following: - 
                          Select Task > Schedule >Indent Task - 
                          Select Task > Schedule > Outdent Task 
 
- 
                          
You can use subtasks and summary tasks to show phases, easily navigate through a large project, and more.
Link tasks in a project
You can link any two tasks in a project to show their relationship, which is called a task dependency. After you link the tasks, every change you make to one affects the other.
- 
                      Select View > Task Views > Gantt Chart. 
- 
                      Hold down Ctrl and select the two tasks you want to link (in the Task Name column). 
- 
                      Select Task > Link the Selected Tasks 
Project supports four kinds of task links to show different relationships.
For more information about task links and scheduling, see How Project schedules tasks: Behind the scenes.
Change your view
- 
                      Select the View tab. 
- 
                      Do one of the following: - 
                          Select the view that you want to use in the Task Views group or Resource Views group. 
- 
                          Select Gantt Chart > More Views to see all the available views, and then select from the options in the More Views dialog box. 
 
- 
                          
 
                         
				 
				