This article describes the issues that are fixed in the Microsoft Project 2013 hotfix package that is dated December 9, 2014. Click the "Hotfix Download Available" button to get the hotfix.

Issues that this hotfix package fixes

  • When you move assignments around in the Team Planner in Project 2013, Project may stop responding or crash.

  • Assume that the Youdao Dictionary application is running. When you copy information or perform actions like resizing columns, task GUIDs are renumbered with the result that task dependencies no longer connect properly.

  • Consider the following scenario:

    • On a Project Server, you have at least two user accounts defined by using the following properties:

      • Both have the same name.

      • One is defined that the User can be assigned as a resource check box is selected and the other is not.

    • You start Project 2013 and connect to Project Server.

    • You add an enterprise resource to a project and you save it.

    • You make some changes in the project and try to save the changes.

    In this scenario, the saving operation may fail.

  • Consider the following scenario:

    • You create a task that contains a long name in a project in Project 2013.

    • In another project, you create a task dependency to the task with the long name.

    • You review the relationship information by clicking the Links Between Projects button in the Project tab.

    In this scenario, the Task column is not scrollable so that you cannot see the whole task name in the Links Between Projects dialog box.

  • Assume that you open and edit a project from Project Server in Project Professional 2013, and the Protected Actuals feature is enabled. You try to change an assignment's time-phased work (remaining work) values. In this situation, you receive the "Your action may result in actuals in this project becoming out of sync with the actuals updated from timesheets" message.

  • Assume that you have at least two Project Web App (PWA) sites, and you have different profiles in Project Professional for each sites. In this situation, when you browse to the Project Center and then click to open a project in Project Professional, the wrong profile may be used and information in the profile is overwritten with the wrong details.

How to get the hotfix

A supported hotfix is available from Microsoft. However, this hotfix is intended to correct only the problems that are described in this article. Apply this hotfix only to systems that are experiencing the problems described in this article. This hotfix might receive additional testing. Therefore, if you are not severely affected by this problem, we recommend that you wait for the next software update that contains this hotfix.If the hotfix is available for download, there is a "Hotfix Download Available" section at the top of this Knowledge Base article. If this section does not appear, contact Microsoft Customer Service and Support to obtain the hotfix. Note If additional issues occur or if any troubleshooting is required, you might have to create a separate service request. The usual support costs will apply to additional support questions and issues that do not qualify for this specific hotfix. For a complete list of Microsoft Customer Service and Support telephone numbers or to create a separate service request, visit the following Microsoft website:

http://support.microsoft.com/contactus/?ws=supportNote The "Hotfix Download Available" form displays the languages for which the hotfix is available. If you do not see your language, it is because a hotfix is not available for that language.

Hotfix information

Registry Information

To use one of the hotfixes in this package, you do not have to make any changes to the registry.

Prerequisites

To install this hotfix package, you must have Project 2013 installed.

Restart requirement

You do not have to restart the computer after you apply this hotfix.

Hotfix replacement information

This hotfix does not replace a previously released hotfix.

This hotfix may not contain all the files that you must have to fully update a product to the latest build. This hotfix contains only the files that you must have to resolve the issues that are listed in this article. The global version of this hotfix package uses a Microsoft Windows Installer package to install the hotfix package. The dates and the times for these files are listed in Coordinated Universal Time (UTC) in the following table. When you view the file information, the date is converted to local time. To find the difference between UTC and local time, use the Time Zone tab in the Date and Time item in Control Panel.x86 versionDownload information

File name

File version

File size

Date

Time

Project2013-kb2910920-fullfile-x86-glb.exe

15.0.4675.1000

32,487,528

13-Nov-2014

22:28

Microsoft Windows Installer .msp file information

File name

File version

File size

Date

Time

Project-x-none.msp

Not Applicable

38,002,688

13-Nov-2014

09:55

Project-x-none.msp file information

File name

File version

File size

Date

Time

Nameext.dll.x64

15.0.4543.1000

367,296

12-Nov-2014

09:19

Nameext.dll.x86

15.0.4543.1000

317,632

12-Nov-2014

09:17

Pjintl.dll

15.0.4609.1000

4,378,312

12-Nov-2014

09:17

Pjintl.dll

15.0.4675.1000

3,557,064

13-Nov-2014

01:50

Winproj.exe

15.0.4675.1000

23,250,080

12-Nov-2014

09:17

x64 versionDownload information

File name

File version

File size

Date

Time

Project2013-kb2910920-fullfile-x64-glb.exe

15.0.4675.1000

34,455,624

14-Nov-2014

06:06

Microsoft Windows Installer .msp file information

File name

File version

File size

Date

Time

Project-x-none.msp

Not Applicable

39,964,672

13-Nov-2014

09:57

Project-x-none.msp file information

File name

File version

File size

Date

Time

Nameext.dll.x64

15.0.4543.1000

367,296

12-Nov-2014

09:17

Nameext.dll.x86

15.0.4543.1000

317,632

12-Nov-2014

09:19

Pjintl.dll

15.0.4609.1000

4,385,480

12-Nov-2014

09:17

Pjintl.dll

15.0.4675.1000

3,564,232

13-Nov-2014

01:59

Winproj.exe

15.0.4675.1000

30,144,680

12-Nov-2014

09:17

References

See the information about the standard terminology that is used to describe Microsoft software updates. The Office System TechCenter contains the latest administrative updates and strategic deployment resources for all versions of Office.

The third-party products that this article discusses are manufactured by companies that are independent of Microsoft. Microsoft makes no warranty, implied or otherwise, about the performance or reliability of these products.

Need more help?

Want more options?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.