Where does the system pull the Variance - Material Account from when closing a Manufacturing Order?


Resolution

When a Manufacturing Order is closed, variances are calculated at that time. Any Variance Account will be pulled from the finished good item.


If the finished good is a Standard Cost Account, the Variance amount will be broken down to the nine different cost buckets:


1. Material

2. Material Fixed Overhead

3. Material Variable overhead

4. Labor

5. Labor Fixed Overhead

6. Labor Variable Overhead

7. Machine

8. Machine Fixed Overhead

9. Machine Variable Overhead


If the Manufacturing Order is for an actual cost finished good, only the Variance - Material Account will be used.


All Variance accounts are being pulled from the finished good item.

This article was TechKnowledge Document ID:31743

TechKnowledge Content

Need more help?

Want more options?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.

Was this information helpful?

What affected your experience?
By pressing submit, your feedback will be used to improve Microsoft products and services. Your IT admin will be able to collect this data. Privacy Statement.

Thank you for your feedback!

×