Prisijunkite prie „Microsoft“
Prisijunkite arba sukurkite paskyrą.
Sveiki,
Pasirinkti kitą paskyrą.
Turite kelias paskyras
Pasirinkite paskyrą, kurią naudodami norite prisijungti.
Anglų
Atsiprašome, tačiau šis straipsnis neprieinamas jūsų kalba.

Data Type    Number

Entry Type    Calculated

Description    The TCPI (to complete performance index) field shows the ratio of the work remaining to be done to funds remaining to be spent, as of the status date.

How Calculated    Microsoft Office Project calculates TCPI as:

TCPI = (BAC - BCWP) / (BAC - ACWP)

Best Uses    Add the TCPI field to a task view to display or filter for the ratio of remaining available budget to be spent to remaining scheduled cost. This can help you see whether you're likely to have excess funds for the task, run out of money, or be right on target.

Example    You have a task with a baseline cost (BAC) of $200, BCWP of $125, and ACWP of $150. The TCPI is 1.5, indicating poor performance up to the status date. This means that to complete the project within budget, performance will need to improve.

Remarks    A TCPI value greater than 1 indicates a need for increased performance for the remaining work of the project in order to stay within budget (so you may need to give up some quality); less than 1 indicates performance can decrease to stay within budget, thus creating opportunities to increase quality or profit.

Reikia daugiau pagalbos?

Norite daugiau parinkčių?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.

Ar ši informacija buvo naudinga?

Kas turėjo įtakos jūsų įspūdžiams?
Paspaudus mygtuką Pateikti, jūsų atsiliepimai bus naudojami tobulinant „Microsoft“ produktus ir paslaugas. Jūsų IT administratorius galės rinkti šiuos duomenis. Privatumo patvirtinimas.

Dėkojame už jūsų atsiliepimą!

×