Prijavite se pomoću Microsoft naloga
Prijavite se ili kreirajte nalog.
Zdravo,
Izaberite drugi nalog.
Imate više naloga
Odaberite nalog pomoću kojeg želite da se prijavite.
engleski
Žao nam je. Ovaj članak nije dostupan na vašem jeziku.

The Finish Variance field contains the amount of time that represents the difference between the baseline finish date of a task or assignment and its current finish date.

There are several categories of Finish Variance fields.

Data Type    Duration

Finish Variance (task field)

Entry Type    Calculated

How Calculated    The Finish Variance field contains "0 days" until the finish date varies from the baseline finish date. Project then calculates finish variance as follows:

Finish Variance = Finish - Baseline Finish

Best Uses    Add the Finish Variance field to a task view when you want to analyze whether your tasks are finishing on, before, or after their planned finish dates.

Example    You set a baseline for your project three months ago, and you now want to review the finish variances on the tasks. You add the Finish Variance field to the Task Sheet view to analyze the task's progress and performance to date.

Remarks    If the Finish Variance is a negative number, the task is scheduled to finish earlier than planned, as shown in the baseline. If the Finish Variance is a positive number, the task is scheduled to finish later than planned. If the Finish Variance is zero, the task is scheduled to finish exactly when planned.

You set a baseline in the Set Baseline dialog box. This copies the current value for the scheduled Finish field into the corresponding Baseline Finish field.

You can use the Tracking Gantt view to see the finish variance shown graphically with Gantt bars. Also, the Variance table includes the Finish Variance field by default.

Finish Variance (assignment field)

Entry Type    Calculated

How Calculated    The Finish Variance field contains "0 days" until the finish date varies from the baseline finish date. Project then calculates finish variance as follows:

Finish Variance = Finish - Baseline Finish

Best Uses    Add the Finish Variance field to the Task Usage view when you want to analyze whether your assignments are finishing on, before, or after their planned finish dates.

Example    You set a baseline for your project three months ago, and you now want to review the finish variances on the assignments. You add the Finish Variance field to the Task Usage view to analyze the assignment's progress and performance to date.

Remarks    If the finish variance is a negative number, the assignment is scheduled to finish earlier than originally planned, as shown in the baseline. If the finish variance is a positive number, the assignment is scheduled to finish later than planned. If the finish variance is zero, the assignment is scheduled to finish exactly when planned.

You set a baseline in the Set Baseline dialog box. This copies the current value for the scheduled Finish field into the corresponding Baseline Finish field.

Da li vam je potrebna dodatna pomoć?

Želite još opcija?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.

Da li su vam ove informacije koristile?

Šta je uticalo na vaše iskustvo?
Kada kliknete na dugme Prosledi“, vaše povratne informacije će se koristiti za poboljšanje Microsoft proizvoda i usluga. Vaš IT administrator će moći da prikupi ove podatke. Izjava o privatnosti.

Hvala vam na povratnim informacijama!

×