The Peak Units fields contains the percentage or number of units to which a resource is assigned at any one time for tasks as distributed over time.

There are two categories of Peak Units fields.

Data Type    Percentage/Number

Peak Units (resource-timephased field)

Entry Type    Calculated

How Calculated    The value in the Peak Units field is the maximum effort a resource is working on all assigned tasks, as shown over a period of time.

Best Uses    Add the Peak Units field to the timephased portion of the Resource Usage view when you want to display the maximum effort for which the resource is designated to work on all assigned tasks over the selected time period.

Example    Jamie is assigned to one task at 25 percent, and to another task at 50 percent. These tasks are both scheduled to take place Tuesday through Friday. In the Resource Usage view, the value in the Peak Units field for Jamie is 75 percent for each day from Tuesday through Friday.

Peak Units (assignment-timephased field)

Entry Type    Calculated

How Calculated    The value in the Peak Units field represents the maximum effort a resource is working on an assignment in the given time period.

Best Uses    Add the Peak Units field to the timephased portion of the Task Usage or Resource Usage view when you want to display the maximum effort for which the resource is designated to work on an assignment, as distributed over time. This is particularly useful when you have applied a work contour other than the default flat work contour. The Peak Units field shows the points in time in which more effort is being applied to the assignment.

Example    You need to review the resource effort for various assignments as distributed over days. In the timephased portion of the Resource Usage view, you add the Peak Units field. For an assignment for three carpenters for five days, you see 300 percent in the Peak Units field across each of the five days. For an assignment for a part-time resource for two days, you see 25 percent in the Peak Units field for each of the two days.

Bạn cần thêm trợ giúp?

Bạn muốn xem các tùy chọn khác?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.

Thông tin này có hữu ích không?

Điều gì ảnh hưởng đến trải nghiệm của bạn?
Khi nhấn gửi, phản hồi của bạn sẽ được sử dụng để cải thiện các sản phẩm và dịch vụ của Microsoft. Người quản trị CNTT của bạn sẽ có thể thu thập dữ liệu này. Điều khoản về quyền riêng tư.

Cảm ơn phản hồi của bạn!

×