Deliverable Type (task field)

Applies To
Project Online Desktop Client Project Standard 2024

Data Type: Number

Entry Type: Calculated

Description: The Deliverable Type field indicates whether the current task has an associated deliverable, and whether that deliverable is produced by the current task or produced by a separate project or task upon which the current task is dependent.

How Calculated: This value can't be changed manually.

  • If the current task has no associated deliverable, the Deliverable Type field displays a value of 0.
  • If an associated deliverable is produced by the current task, this field displays a value of 1.
  • If an associated deliverable is produced by a separate project or task upon which the current task is dependent, this field displays a value of 2.

Tip

If you would prefer to display this information as text, you can customize a calculated field and insert the calculated field instead of Deliverable Type. Base your calculated field on the Deliverable Type field and use the following formula:

Switch([Deliverable Type]=0,"NA",[Deliverable Type]=1,"Deliverable",[Deliverable Type]=2,"Dependency")

Best Uses: Add the Deliverable Type field to a task sheet so that you can tell at a glance whether an associated deliverable is produced by the current task or by a separate project or task upon which the current task is dependent.

Remarks: You can only associate one deliverable with any one task, either as a deliverable produced by that task or as a deliverable produced by another task or project upon which that task is dependent.

To make project deliverables visible on a task sheet, include at least one of the following fields:

  • Deliverable Type: Indicates whether the current task has an associated deliverable, and whether that deliverable is produced by the current task or by a separate project or task upon which the current task is dependent.
  • Deliverable Name: Displays the name or title of the associated deliverable.
  • Deliverable Start: Displays the scheduled start date of the associated deliverable.
  • Deliverable Finish: Displays the scheduled finish date of the associated deliverable.
  • Deliverable GUID: Displays the unique identification code of the associated deliverable.