Share Resources dialog box

Applies To
Project Online Desktop Client Project Standard 2024 Project Professional 2021 Project Standard 2021 Project Professional 2019 Project Standard 2019 Project Professional 2016 Project Standard 2016

Use the Share Resources dialog box to set preferences for sharing resources with other projects. You can:

  • Turn on or turn off resource sharing.
  • Choose which project file resources are being shared from.
  • Specify which file takes priority if the resource information in the two files conflicts.

Dialog box location

On the Resource menu, point to Resource Pool, and then select Share Resources.

Details

Resources for section

Use own resources: Specifies that you want the active project to use its own resources. This option is selected by default.

Use resources: Specifies that you want the active project to use resources from another project.

From: Specifies the name of the open project from which you want to share resources. This box is available only if the Use resources option is selected.

On conflict with calendar or resource information section

Pool takes precedence: Specifies that if there's conflicting information regarding a resource between the active (sharer) project and the resource pool project, the information in the resource pool project should be respected. For example, if the max units for a resource in the sharer project are 100 percent and the max units for the same resource in the pool are 75  percent, and you indicate that the pool takes precedence, then the value of 75 percent is retained as the max units for that resource. This option is selected by default.

Sharer takes precedence: Specifies that if there's conflicting information regarding a resource between the active (sharer) project and the resource pool project, the information in the active (sharer) project should be respected.