The Remaining Tasks field shows the total number of scheduled subtask that remain to be completed for a summary task on a given day. If the project summary task is displayed, the Remaining Tasks field shows the total number of scheduled tasks and subtasks that remain to be completed on a given day for the entire project.

Data Type    Number

Entry Type    Calculated

How Calculated    To calculate the Remaining Tasks field, Project totals the number of subtasks under a summary task, and then subtracts the number of subtasks that have a finish date on that day or earlier.

To calculate the Remaining Tasks field for the project summary task, Project totals the number of scheduled tasks and subtasks for the entire project, and then subtracts the number of subtasks and tasks that have a finish date on that day or earlier. Note: Project includes subtasks and regular tasks in this calculation, but it does not include actual summary tasks (a task that includes subtasks).

Best Uses    Create summary tasks that contain one or more subtasks. Add the Remaining Tasks field to the timephased portion of the Task Usage view when you want to display how many scheduled subtasks remain to be completed on a given day for a summary task.

Example    The "Write proposal" summary task has 3 subtasks: “Write”, “Edit,” and “Revise.”

The “Write” task is scheduled for days 1 and 2.

The “Edit” task is scheduled for day 3.

“Revise” is scheduled for days 4 and 5.

You add the Remaining Tasks field to the time-phased portion of the Task Usage view. At day 1, it is 3. At day 2, it is 2.

At day 3, it is 1. At day 4, it is 1. At day 5, it is 0.

Remarks

  • Subtasks will always display a 1 in the Remaining Tasks field before the finish date, and a 0 on the finish date.

  • You can turn on the project summary task on the Advanced tab of the Project Options dialog box.

Top of Page

Bạn cần thêm trợ giúp?

Bạn muốn xem các tùy chọn khác?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.

Thông tin này có hữu ích không?

Điều gì ảnh hưởng đến trải nghiệm của bạn?
Khi nhấn gửi, phản hồi của bạn sẽ được sử dụng để cải thiện các sản phẩm và dịch vụ của Microsoft. Người quản trị CNTT của bạn sẽ có thể thu thập dữ liệu này. Điều khoản về quyền riêng tư.

Cảm ơn phản hồi của bạn!

×